Board of Trustees for the Ohlone Community College District

Board of Trustees Update
As of the January 11, 2006 Board Meeting

  • The Board ratified the contract for Structural Steel for the Ohlone College Newark Center Project with SME Steel Contractors for the amount of $4,316,500.00.
  • The Board was notified that MBT Architecture, the architect designing the Ohlone College Newark Center for Health Sciences and Technology, has changed their name to Perkins+Will as of November 4, 2005.
  • The Board awarded the remaining bids for the Ohlone College Newark Center for Health Sciences and Technology to Best Inc., for $2,777,500.00 for metal panels/sheet metal/louvers/exp. joint assys;  to Deck West, Inc. for $556,140.00 for metal decking;  and Glazier Iron Works, Inc. in the amount of $1,140,000.00 for iron and steel stairs.
  • The Board ratified two China cooperation agreements between the Ohlone Community College District and Zhejian Changzheng College and the Shanghai Theater Academy.
  • The Board completed its' self evaluation and provided a summary of the feedback received.
  • The Board agreed to schedule a workshop at a later meeting date in order to bring in a facilitator to assist with establishing the Board's Goals for 2006.

If you would like to review any of the corresponding documents , please visit the Board of Trustees Documents Index for this meeting.

Agenda Items for Future Meetings

  • Foreign Languages Department Presentation  - 1/25/06
  • Enrollment Report  - 2/22/06
  • Title III Project Presentation  - 2/22/06
  • Fine and Performing Arts Division Presentation  - 3/29/06
  • Deaf Studies Division Presentation  - 4/26/06
  • OCNC Education Plan Update  - 5/24/06

Date for Next Meetings

  • January 25, 2006  - Child Development Center conference room.
Rich Watters. Jan Giovannini-Hill. Garrett Yee. Greg Bonaccorsi. Teresa Cox. Vivien Larsen. Ishan Shah.